Galileo OSNMA Receiver Testing: Authentication States and Test Evidence

Galileo OSNMA receiver testing checks whether a receiver authenticates the intended navigation data, handles missing or rejected authentication information, and applies the declared navigation-output policy. An “OSNMA enabled” setting or a valid position fix cannot establish all three.

OSNMA authenticates Galileo navigation data carried through I/NAV, with authentication information broadcast on E1-B. Initial Service became operational on 24 July 2025. [1] A useful test therefore needs an explicit service/document baseline, trust material, time assumptions and receiver evidence.

Keep the claim precise: OSNMA provides data authentication. It does not by itself authenticate the measured ranges or the resulting position, velocity and time (PVT), prevent every spoofing case, or protect against jamming. [2]

Use jamming versus spoofing for the wider threat distinctions and GNSS Simulation 101 for the test-method learning path. This guide focuses on authentication evidence and output use.

1. Define exactly what the test will prove

Write separate requirements for navigation-data authentication, receiver reporting and application behavior. Identify the Galileo data types under test and which authenticated data the application requires before qualifying an output.

Galileo’s Authentication Data and Key Delay (ADKD) identifies the authenticated data and delay class. ADKD 0 and 12 cover I/NAV ephemeris, clock and status data; ADKD 4 concerns timing-conversion parameters. [2] Do not treat successful authentication of one type or satellite as coverage of every input to a multi-constellation solution.

Message authentication and navigation acceptance are separate checks Navigation and OSNMA data pass through checks using applicable trust material and time prerequisites to produce authentication evidence. Ranges and other inputs feed the navigation solution separately. Application policy combines both evidence paths with validity and freshness checks. Authentication evidence supports a separate output decision Navigation + OSNMA data Data set, tag and key inputs Preserve identity and epochs OSNMA verification Applicable trust and time checks Protocol and data association Authentication evidence Result for identified data Not a PVT accuracy verdict Ranges + other inputs Observations and sensor data Separate measurement checks Navigation solution PVT and contributing inputs Truth, validity and output age Application output policy Qualify, degrade or withhold According to declared rules Conceptual evidence paths, not a receiver implementation or product interface.
Test both evidence paths and their use by the application. Scroll horizontally on smaller screens.

A receiver may correctly authenticate navigation data while its position is wrong because of other inputs or measurement errors. Conversely, an accurate position does not prove that authentication ran or that the authenticated data contributed to that solution. Authenticated data still require separate satellite-health and navigation-applicability checks. [5]

2. Separate broadcast status, authentication results and output use

The broadcast NMA Status (NMAS) includes Test, Operational and Don’t Use, plus a reserved value. These describe the service information; they are not the receiver’s per-data-set verification result. Interpret status only after the required verification. [3]

Evidence categories for a test report—not universal receiver status labels
Evidence layer Record What it does not establish
Feature configuration OSNMA mode, firmware, settings and retained state. Enabling the feature does not prove successful authentication.
Broadcast status Native NMAS, chain/public-key status and their verification state. An Operational indication alone does not authenticate a data set.
Trust processing Applicable material and verification or retrieval events. A verified key alone is not a completed navigation-data authentication.
Data authentication Target satellite, ADKD, data identity, result and completion event. One successful data set does not qualify every navigation input.
Unable to authenticate Missing information, time prerequisite or rejected verification, distinguished by cause. No new success does not automatically mean a cryptographic mismatch or confirmed spoofing.
Application use Actual navigation inputs, coverage, freshness and output decision. A position-valid flag does not identify the authentication coverage.

Scroll horizontally to view all columns. Preserve the native receiver fields and document any report-level mapping.

Interpret chain/public-key status (CPKS) together with NMAS, identifiers and transition phase. A revocation indication can refer to old material while current replacement material is usable in the operational phase. [3] A rule that rejects everything whenever a field contains “revoked” can therefore give the wrong result.

3. Freeze the trust, time and input setup

Document the retained state and the time prerequisite

Inventory the Merkle root, public key, TESLA material and their applicability for the chosen epoch. Record provenance, identifiers, verification and persistence. Generic cold/warm/hot GNSS reset names do not specify which OSNMA material survives.

Declare the local GST source, uncertainty, holdover assumptions and authentication mode. Apply the mode-specific checks in the Receiver Guidelines, including §2.1, §5.3.1 and Annex C. A plausible displayed time is not proof that the delayed-disclosure time prerequisite is met. [4]

For repeated runs, freeze the test-data version and hash, cryptographic fixture, reset procedure and input start. Distinguish applicable historical test material from current operational material. Record whether network retrieval is allowed and what it changes.

Choose the injection boundary explicitly

  • Protocol-level input: evaluate parsing, state transitions and authentication logic through a documented interface. This bypasses the RF and acquisition chain.
  • Conducted RF: evaluate the receiver chain under verified signals, levels and timing. Confirm that the RF source carries the intended OSNMA-bearing data and consistent navigation content.
  • Recorded RF replay: retain capture epoch, bandwidth, metadata and trust/time conditions. Successful playback does not by itself establish that the receiver’s historical-epoch authentication setup is correct.

Official vectors have a specific role. Guidelines Annex B provides historical I/NAV CSV vectors for protocol logic, not RF/IQ recordings or service-performance benchmarks. Their local-GST setup must match the vector epoch under the documented test arrangement. [4] Check the official in-force documents and Annex B download entry ; preserve the supplied package and material versions.

The official vector coverage includes configurations, key/chain management, Merkle-tree renewal and an alert case. [6] These lifecycle cases are not inherently authentication-failure vectors. Label modified or intentionally incomplete fixtures as custom cases, and keep them separate from the original package.

4. Build a receiver test matrix with explicit expected behavior

The following is a planning template. Select cases supported by the DUT and test arrangement, then attach the applicable protocol requirement and the separate application rule. Keep the known-good baseline before and after each exception case.

Authentication, missing information and lifecycle behavior require different verdicts
Case Controlled condition Required evidence
Startup and retained state Known trust/time fixture; vary the explicitly retained OSNMA material. Retrieval and verification sequence; no premature authentication claim for new data.
Known-good authentication Matched input, epoch, applicable material and supported ADKD. Successful result bound to the intended satellite/data set; application coverage evaluated separately.
Controlled verification mismatch A documented custom fixture targeting the intended verification stage while satisfying earlier checks. Rejection and reason at that stage; affected information excluded from authentication success.
Missing authentication data Declared tag/key/DSM omission, with navigation-data reception characterized separately. Waiting or unavailable state distinguished from mismatch; treatment of still-valid authenticated data recorded.
Time prerequisite not met Controlled uncertainty or offset outside the applicable processing condition. Time-check response and application reporting; no bypass presented as operational validation.
Renewal, revocation and restart Approved lifecycle fixtures and explicitly applicable old/new material. Verified status, correct transition and material use, plus persistence behavior after restart.
Don’t Use and alert handling Verifiable service-status or alert fixture with its documented recovery path. Protocol response, application notification and required trust update; no assumed automatic recovery.
Recovery and output use Verified return of known-good input with the intended trust/time state. New authentication evidence, qualifying output and sustained coverage measured separately.

Scroll horizontally to view all columns. This template does not assert that every instrument or receiver supports every case.

Identify where an input was rejected. A page discarded during decoding or CRC checking is not evidence that the MAC-verification path detected a mismatch. Likewise, a missing tag does not prove invalid navigation data or require every application to stop PVT immediately.

5. Preserve evidence at the data-set level

Retain native logs and make the analysis mapping reviewable. Request the following where the DUT exposes them; missing observability limits the claim rather than licensing an inferred success:

  • Input: fixture/capture hash, injection boundary, epoch, delivery exceptions and source/RF verification.
  • Trust and time: material identifiers and applicability, local-GST provenance/uncertainty, retrieval events and reset state.
  • Authentication: transmitting and target satellite identities where relevant, ADKD, data-set identity, native status and verification stage, completion time and failure/wait reason.
  • Output: solution epoch, contributing navigation data, validity, age, application classification, alarms and record-arrival time.

A transmitting satellite and the satellite whose data are authenticated can differ. Use the target identity and the data/time association rather than counting OSNMA-bearing signals as authenticated navigation satellites.

The Initial Service SDD specifies a minimum equivalent tag length of 40 bits for a given navigation data set. [5] An isolated tag-success flag is insufficient evidence unless the required length and data association are established. Do not pool unrelated satellites, ADKD types or changed data sets to reach a threshold.

Use the receiver’s documented data identity and applicability rules when linking authentication evidence to PVT. If the logs expose only a general authentication indicator, report that observed indicator and the resulting evidence limit. Use PVT log validation for epoch, validity and output-age handling.

6. Measure authentication and recovery time separately from TTFF

Define whether a timing metric ends at an internal event, a solution epoch or delivery of a complete report. Specify the start event and retained material. Avoid an undefined “time to authenticated fix” label that combines several different endpoints.

Illustrative report-delivery timeline—arbitrary values, not a product result or service target
Aligned bench time Observed event Interpretation
0 s Known-good input restoration is independently verified; trust/time fixture is declared. Start of this recovery measurement.
6 s An ordinary PVT report arrives. Output delivery resumed; authentication coverage is not established by this event.
45 s First report confirms a newly authenticated target data set. 45 s to delivery of that authentication evidence.
52 s A complete output report first meets all declared application criteria. 52 s to the first qualifying delivered output.
62 s Reports establish a full 10 s qualifying interval, starting at 52 s. Sustained qualification is confirmed at 62 s; the declared gap/age rules also apply.

Scroll horizontally to view all columns. Times describe observed delivery events on one aligned bench clock; retain the associated navigation-data and solution epochs separately.

For this example, 6 s, 45 s, 52 s and 62 s answer different questions. These are not pure algorithm processing times. Later authentication cannot retroactively qualify an earlier real-time output at its delivery time. If the required reports never establish the endpoint before the test limit, retain the timeout. Do not compute recovery statistics from successful attempts alone.

7. Apply separate protocol and application acceptance rules

Before execution, define the relevant authenticated data, permitted data age, satellite/input coverage, output freshness, fallback behavior, alarm delivery and recovery windows. Previously authenticated data may remain usable while still valid; loss of a new tag is not automatically expiry. [5]

  • Input acceptance: the intended data, trust/time fixture and injection/RF conditions are established.
  • Protocol acceptance: the receiver handles the selected case according to the applicable requirements, with traceable data-level results.
  • Application acceptance: the declared data-use policy, classification, warnings, accuracy and delivery rules are met.

A correctly rejected custom mismatch can be a protocol-test pass. Navigation may continue, degrade or be withheld according to the separately declared application policy. Neither continued PVT nor suppression is universally the right outcome.

Mark a criterion failed when sufficient evidence demonstrates a breach. Mark it not verified when input realization, log coverage or data-to-solution mapping is insufficient. A confirmed input fault can fail an input requirement without proving a DUT failure. Retain every run, exception and timeout.

Service performance levels in the SDD have specified assumptions and statistical definitions. They are not generic per-run receiver thresholds or a product certification. [5]

8. Match the OSNMA test requirements to a confirmed configuration

Use the GNSS spoofing and interference testing solution to define the wider resilience bench. The ASG8000 page lists OSNMA validation within supported resilience workflows. Confirm the exact OSNMA data source, trust configuration, case coverage and receiver observations for the proposed arrangement.

Galileo RF support alone does not establish a valid OSNMA test stream. Before selecting equipment, request evidence for the required input boundary, data/time consistency, supported lifecycle or exception cases, control interfaces and output evidence. Confirm responsibilities for any external data source or analysis tool.

Include a small known-good acceptance case and its expected evidence in the configuration review. Expand to the required matrix after the basic chain is demonstrated.

Galileo OSNMA receiver testing FAQ

Does OSNMA authenticate the receiver’s position?

OSNMA authenticates navigation data. Range errors, other constellations, sensors and receiver processing still affect the solution. Test data authentication and PVT acceptance separately.

Does Operational status mean the receiver has authenticated its data?

No. Broadcast status and the receiver’s verified data-set result are separate evidence. Confirm the required status verification and the data authentication itself.

Can official OSNMA vectors replace RF testing?

They assess protocol implementation through their documented data format. They do not exercise the RF/acquisition chain or establish service performance. Use a verified RF arrangement when those are part of the claim.

Does one missing tag prove spoofing?

No. Separate missing information, decoding/CRC rejection and a verification mismatch. Diagnose with the input, receiver and time/trust evidence before assigning a cause.

Is any Galileo-capable simulator suitable for OSNMA tests?

Confirm the actual OSNMA-bearing data, epoch, trust setup and supported cases. Constellation support alone does not establish those capabilities.

Plan a reviewable OSNMA receiver test

Share the receiver model and firmware, authentication mode, available logs and the cases you need to verify. State whether the goal is protocol logic, the full RF receiver chain or application output behavior.

Request a configuration review to establish the proposed input source, trust/time setup, supported test coverage and evidence deliverables. Detailed interface files and fixtures can follow during the review.

Official references and document baseline

Checked 20 October 2026: the GSC in-force directory lists SDD v1.0 (July 2025), SIS ICD v1.1 (October 2023) and Receiver Guidelines v1.3 (January 2024). Freeze the applicable versions and review service notices when preparing a campaign.

  1. GSC: OSNMA service overview and Initial Service date .
  2. GSC FAQ: authenticated data, processing and authentication boundaries .
  3. OSNMA SIS ICD: status semantics and lifecycle processes .
  4. Receiver Guidelines v1.3: time prerequisites and Annex B vectors .
  5. OSNMA SDD: usage conditions, equivalent tag length and performance definitions .
  6. GSC: vector coverage in the Guidelines update .

Check the current OSNMA document register and Annex B download entry →