GNSS Test Equipment · Procurement and Delivery Acceptance

GNSS Simulator FAT and SAT: Configuration and Acceptance Checklists

GNSS simulator acceptance testing should establish what was delivered, which requirements were demonstrated and whether the installed test bench can repeat the agreed workflow. A successful receiver fix is useful evidence, but it is only one part of that decision.

A factory acceptance test (FAT) checks the agreed configuration before shipment or release. A site acceptance test (SAT) checks the delivered configuration and relevant workflows after installation at the customer site. Define the scope, locations, witnesses and required records for the project.

Use this as a planning template. The checklists, workflow and numerical example below are suggested material to adapt and agree. They are not an executed acceptance report, a standard vendor procedure or universal contractual criteria.

Start with the GNSS simulator selection guide if the configuration is still being chosen. Use this article to turn the selected requirements into reviewable delivery evidence.

1. Freeze a baseline that can actually be tested

Translate the purchase requirements into a configuration record and a test matrix. Give each requirement an identifier and link it to a procedure, acceptance criterion, responsible party and expected evidence.

“Supports GPS L1” needs more definition than “the GPS option is enabled.” Identify the required signal component, simultaneous signal combination, RF output and scenario conditions. Similarly, an interface name should identify the physical connection, protocol, data definition and supported operating mode.

  • Hardware: model, serial numbers, RF paths, ordered modules, connectors and supplied accessories.
  • Software: application and firmware versions, installed signal licences, options and entitlement details relevant to operation.
  • Test definitions: scenario files, starting epoch, trajectory, signal allocation, expected events and retained truth outputs.
  • External dependencies: control computer, DUT, references, cables, splitters, instruments and customer-supplied systems.
  • Acceptance method: measured quantity, reference plane, test points, limits, uncertainty treatment and result categories.
  • Delivery responsibilities: who supplies, installs, verifies and supports each required element.

Keep the approved revision with the test record. A product photograph or demonstration setup does not define whether a PC, RF cable or reference instrument is included in the order.

2. Separate three acceptance conclusions

Source and configuration acceptance concerns the delivered simulator: installed hardware, licences, signal combinations, outputs and the source properties covered by the agreed measurements.

Bench acceptance concerns the installed path and workflow: RF delivery, DC compatibility, external timing, control, data collection and analysis. The source and measurement reference planes must be identified.

DUT performance concerns the receiver or navigation system being tested. Its error, acquisition time or recovery behavior is a separate result. A DUT failure can be a valid result from a correctly functioning test system.

Match the evidence to the claim. A software spectrum view can represent generated digital samples, while a receiver-deviation display compares DUT output with truth. For example, the Skydel manual explicitly distinguishes those display functions.[1] Neither display alone establishes every physical RF property at a connector.

The NSG8000 laboratory configuration guide explains the source, RF path and receiver-evidence boundaries in more detail.

3. Carry the evidence from FAT through SAT

Use the FAT package as the reference for site installation. Record changes introduced by shipping, installation, software updates and customer equipment, then identify which checks must be repeated.

Suggested GNSS simulator acceptance workflow An agreed configuration baseline leads to factory acceptance and then site acceptance after shipping and installation. Evidence review leads either to handover or to correction and impacted retests followed by another review. Acceptance follows the delivered configuration Agreed baseline FAT SAT Handover record Correct and retest Evidence review Requirements, configuration, rules Check before shipment or release Check installed site workflow Accepted scope and retained files Preserve failures and changes Required evidence accepted? Ship and install Open item Repeat impacted checks; review new evidence All required items accepted under the agreed plan
Suggested workflow. Identify the FAT and SAT procedures affected by a correction; retain the original and replacement records under distinct run IDs.

A repeat run should use the saved baseline rather than an operator's recollection of the demonstration. Retain both the configured settings and the available records of what actually ran.

4. Suggested factory acceptance test checklist

Agree the test cases and witness arrangements before FAT. The following rows are examples to tailor; options and interfaces apply only where included in the accepted configuration.

Example FAT work items and evidence to retain
Item Check Evidence
FAT-01: identity and delivery scope Compare hardware, serial numbers, modules and accessories with the agreed register. Configuration inventory, serial records and recorded differences.
FAT-02: software and licences Verify versions and ordered entitlements, including activation and operating dependencies. Version report, entitlement record and demonstrated access to ordered functions.
FAT-03: required signal combinations Run the required simultaneous signals, channel allocation and RF routing. Saved scenario, as-run status, output map and evidence appropriate to each signal claim.
FAT-04: source measurements Perform the agreed RF and timing verification at defined points using suitable methods. Instrument results, reference planes, corrections, uncertainty and decision rule.
FAT-05: scenario and truth Load the selected static/dynamic cases and verify required events and exported truth. Input files, units, coordinate/time definitions, event timeline and truth records.
FAT-06: ordered interfaces Demonstrate applicable control, automation, HIL and external-reference functions. Commands, interface settings, timestamps and defined latency/trigger measurements where required.
FAT-07: restoration and records Reload the saved configuration and repeat the agreed baseline after the specified restart procedure. Reload steps, run IDs, logs, analysis and documented result differences.

Scroll horizontally to view all columns. Replace the example IDs with project requirement and procedure identifiers.

Self-test and a reference receiver can support functional checks. Source accuracy claims need the specified verification method. In particular, total RF power, a per-satellite component level and receiver-reported C/N₀ are different quantities.

For weak spread-spectrum signals, use an applicable manufacturer-supported measurement procedure and suitable calibrated equipment. An ordinary power reading may not resolve the required quantity at the intended level. Include path corrections and measurement capability in the plan.

5. Agree how measurement results become decisions

Specify the measured quantity, test points, reference plane, applicable corrections and uncertainty evaluation before assigning pass/fail. NIST explains that metrological traceability belongs to a measurement result and its documented calibration chain; it does not automatically make the result suitable for every purpose.[2]

Keep the specification limit separate from the acceptance decision rule. JCGM 106 discusses how uncertainty affects conformity decisions and how acceptance limits can differ from tolerance limits.[3] Record the selected rule with the result.

Hypothetical example: RF-level error with a review category

Assume a project defines a permissible error interval of −0.50 to +0.50 dB for one specified RF-level measurand. The parties choose this example non-binary rule: accept when the reported interval e ± U lies wholly inside the limits; fail when it lies wholly outside; otherwise hold for review.

Here e is measured error and U is the reported expanded uncertainty. Record its coverage factor, evaluation method and applicable conditions. The chosen rule is illustrative; ILAC G8 describes multiple decision-rule approaches.[4]

Example values and project-defined decisions, not simulator specifications
Case Measured error e Expanded uncertainty U Interval and decision
A +0.28 dB 0.12 dB [+0.16, +0.40] dB: accept under the stated rule.
B +0.42 dB 0.15 dB [+0.27, +0.57] dB: hold for review; the interval crosses a limit.
C +0.70 dB 0.10 dB [+0.60, +0.80] dB: fail under the stated rule.

Scroll horizontally to view all columns. “Hold for review” is not a pass. This example does not assign a universal coverage probability or risk level.

Retain unresolved results until the agreed disposition is complete. A new measurement should follow a justified correction or revised method, with the earlier evidence preserved.

6. Suggested site acceptance test checklist

SAT checks the installed configuration against the FAT baseline and the agreed site requirements. Identify what changed, then repeat the baseline and affected measurements. A factory result remains tied to its original setup and conditions.

Example SAT checks after delivery and installation
Item Site check Evidence
SAT-01: delivered identity Match received hardware, versions and licences to the released FAT register; inspect recorded shipping or installation issues. Receipt inventory, condition record and configuration differences.
SAT-02: installed RF/DC path Verify actual cables, splitters, switching, losses, bias arrangements and DUT reference plane. As-built connection diagram, path measurements/corrections and relevant input checks.
SAT-03: timing and references Check the site's reference source, lock state, trigger routing and required epoch mapping. Reference identity, timing definitions and measurements appropriate to the claimed alignment.
SAT-04: control and data Run the supported workflow on the installed host, with the actual DUT and required instruments. Interface records, command/result logs, run IDs and exported files.
SAT-05: baseline and affected cases Repeat the agreed baseline and the cases affected by installation differences. Matched scenario revisions, measured results, comparison method and explanation of differences.
SAT-06: operation and recovery Have the nominated operator restore a saved setup, execute a case and recover its report. Operator procedure, saved configuration, successful file retrieval and remaining support items.

Scroll horizontally to view all columns. The site plan determines which FAT checks repeat and which new integration checks are required.

External-reference lock confirms a defined lock condition; additional evidence is needed for an absolute timing claim. Similarly, the same receiver result at both sites is not a complete source calibration.

Use the integrated GNSS test-system solution to review the RF, control, timing and evidence responsibilities of a larger bench.

7. Keep open items and retests visible

For each unresolved item, record the requirement, observed result, evidence file, impact, owner, action and planned review. Distinguish failed, not run, awaiting evidence and justified not-applicable items. An unperformed test does not become a pass because a related demonstration succeeded.

When a correction changes hardware, firmware, software, licences, scenarios or the RF path, issue a new baseline revision and identify affected tests. Repeat those checks and any agreed regression cases. Preserve the original result and link the new evidence to the corrective action.

Do not rerun a failing test repeatedly and retain only a favorable outcome. Apply the predefined repeat-count and result-handling procedure. If there was no valid input or measurement, document why the run is invalid rather than silently discarding it.

Any deferred or excluded item should have an explicit disposition in the acceptance record. The final accepted scope must be understandable without relying on a verbal agreement made during the demonstration.

8. Deliver an evidence package the customer can use

Keep the handover package organized by configuration revision, requirement and run ID. A useful project-defined package includes:

  • Released configuration: delivered serial numbers, versions, installed entitlements, options and responsibility register.
  • Test records: approved procedures, actual conditions, measured values, result decisions and witness records where required.
  • Reusable inputs: scenario files, trajectories, scripts, file versions/checksums and setup instructions.
  • Supporting evidence: raw logs, truth data, analysis settings, applicable calibration records and uncertainty information.
  • As-built documents: connections, reference planes, RF corrections, timing mapping and customer-equipment dependencies.
  • Operation and support: manuals, backup/restore procedure, agreed training, support scope and open-item dispositions.

Check that the customer's operator can access the files and reproduce the agreed baseline. A report containing “pass” without its configuration, method and evidence leaves the laboratory with an incomplete starting point.

Record acceptance against the defined requirements and conditions. Receiver qualification, accreditation, certification and future software configurations each require their own applicable evidence and scope.

Frequently asked questions

Does FAT replace SAT?

FAT supplies pre-delivery evidence for its recorded configuration. SAT checks the installed site workflow and relevant changes. Define their respective scopes and repeated cases in the project plan.

Does a receiver fix prove the simulator meets its RF specifications?

It demonstrates reception under the tested conditions. Physical RF specifications require measurements appropriate to the specified quantity, level, frequency and reference plane.

Should every project use the numerical limits in this article?

No. The values and decision rule are examples. Use the ordered specifications, applicable methods, measurement capability and agreed acceptance plan for the actual system.

Define the configuration and its acceptance evidence

Share your DUT, signal matrix, RF architecture, existing instruments and integration requirements. Include the proposed FAT/SAT locations, witness needs, required deliverables and unresolved acceptance questions.

Request a configuration and acceptance-scope review covering equipment responsibilities, representative test cases and the records needed at handover.

Explore the GNSS simulation product family or continue through the GNSS Simulation 101 hub.

Technical references

  1. Safran: Skydel Interface Manual — distinguishes digital-spectrum displays and receiver-deviation views; these examples do not establish other products' functions.
  2. NIST: Metrological Traceability FAQ — traceability of measurement results and suitability for the intended purpose.
  3. JCGM 106:2012 — measurement uncertainty, tolerance limits and acceptance decisions.
  4. ILAC G8:09/2019 — decision-rule selection, documentation and conformity statements.

This article provides an example planning framework. The agreed specification, test plan, current equipment documentation and project delivery scope define the actual acceptance work.